DSWA’s  Administrative Office is now located at 601 Energy Lane, Dover DE 19901 

Replacement of Scales at the Pine Tree Corners Transfer Station

Five (5) copies of Sealed Bids, in response to Request for Bids for Replacement of Scales at the Pine Tree Corners Transfer Station, located at 276 Pine Tree Road, Townsend, Delaware 19734, will be received by the Delaware Solid Waste Authority (DSWA) at the DSWA’S Dover office, 601 Energy Lane, Dover, Delaware, until 2:00 p.m., on Wednesday, September 25, 2024, at which time all Bids will be opened and read aloud.  DSWA may extend the time and place for the opening for Bids by providing at least two (2) calendar days notice by certified mail, fax, or email to any Bidders who DSWA has recorded as having received an RFB.  If the Bid is submitted by mail or other delivery system, the sealed envelope containing the Bid shall be enclosed in a separate envelope plainly marked on the outside with the notation “Bid Enclosed.”  Bids delivered by any means other than by mail or personal delivery shall be rejected.

 

The project includes replacing the main facility scales at the Pine Tree Corners Transfer Station.  The work includes, but is not limited to, surveying before, during, and after construction; demolition and removal of existing scales; site work and grading; construction of scale approaches, installation of new scales; installation of new gates and intercoms; and appurtenant items as described in the Project Manual.  Additional information and details regarding the scope of work are included in the Project Manual.

 

A copy of the RFB for Contract C-24-895-NT may be obtained by emailing smg@dswa.com or submitting a request at https://dswa.com/resources/rfpbids/request-for-bidsproposals/ on or after August 13, 2024.  DSWA will not be responsible for full or partial sets of the Project Manual obtained from any sources other than stated above, or in the Project Manual, nor shall BIDDER rely upon such other sources or information.

 

A non-mandatory Pre-Bid Meeting has been scheduled for Wednesday, August 21, 2024, at 10:00 a.m.  The location of the Pre-Bid Meeting is at the DSWA’S Dover office located at 601 Energy Lane Dover, Delaware. A non-mandatory site tour of the Pine Tree Corners Transfer Station will take place immediately after the Pre-Bid meeting. It is the responsibility of the BIDDER to obtain an understanding of site conditions before preparing a bid.  Accordingly, BIDDERS are encouraged to attend the pre-bid meeting and/or schedule a site visit.

 

Each Bid, in excess of $200,000, shall be accompanied by a certified check or surety company bid bond, drawn to the order of the Delaware Solid Waste Authority on the form provided in the Project Manual and in an amount not less than ten percent of the “total bid price” as a guarantee that if the Bid is accepted, a contract will be entered into and the performance thereby properly secured.  Additional information regarding bid security appears in the Project Manual.

 

The BIDDER must submit, with its BID, documentation indicating it is licensed to conduct business in the State of Delaware and BIDDER must meet and comply with all state, local, and federal laws, regulations, ordinances, and requirements in the scope of their Work and comply with any and all licensing and permitting requirements.  All subcontractors used by the BIDDER must be licensed to conduct business in the State of Delaware prior to conducting any work on-site.  A copy of the form of the Agreement is contained in the Project Manual and will be awarded to the lowest responsive and responsible BIDDER who has neither been disqualified nor rejected pursuant to the terms of the Project Manual, and, which in DSWA’s judgement best serves its purposes.

 

The successful Bidder will be required to execute the Agreement, to furnish a performance bond and payment bond for the work each in the amount of one hundred percent (100%) of the “Total Bid Price” if the bid amount is more than $200,000, and to execute a Hold Harmless Agreement on forms provided in the Project Manual.  The successful bidder will also be required to furnish evidence of insurance coverage as required by the Project Manual and otherwise comply with terms and requirements of the Project Manual.

 

DSWA reserves the right to accept or reject any or all Bids which in its judgment is in the best interest of DSWA, and to waive any irregularities or informalities in the Bid or Bid process, and all BIDDERS are notified that such acceptance or rejection or waiver shall be without liability on the part of DSWA for any action brought against DSWA, any or all of its directors, or any DSWA agent, representative, officer or employee, brought by any BIDDER because of such acceptance or rejection or waiver, nor shall any Bidder seek any recourse of any kind against such entity or individuals because of such acceptance or rejection or waiver.  Every BID prepared in response to this notice shall be prepared at the sole cost and expense of the BIDDER and shall be prepared by the BIDDER with the express understanding that any and all claims to reimbursement for the cost and expense of its preparation are waived.  The submittal of a bid in response to this notice shall constitute an agreement of the Bidder to all the provisions set forth in this notice and the Project Manual.

 

Five (5) copies of Bid shall be submitted to DSWA.  The Bids shall be, sealed, marked, and addressed as follows:

Delaware Solid Waste Authority

601 Energy Lane

Dover, Delaware 19901

Attention: Christopher Velazquez

Bid For: Replacement of Scales at the Pine Tree Corners Transfer Station

Contract C-24-895-NT

 

No BIDDER may withdraw their Bid within one-hundred-twenty (120) days after the actual date of opening thereof, except as may be authorized by the Project Manual.

 

The Project Manual explains the process by which prospective Bidders may submit questions about the meaning or intent of the Project Manual.  Please contact DSWA prior to the bid opening if you wish to schedule a site tour.

 

All other inquiries regarding this work shall be directed to:

Christopher Velazquez                       and                  Simone George

Project Engineer                                                         Administrative Assistant

Phone:  302-739-5361                                                 Phone:  302-739-5361

Fax: 302-739-4287                                                     Fax:  302-739-4287

E-mail:  cav@dswa.com                                             E-mail:  smg@dswa.com

Route 5 Transfer Station Tipping Floor Trench Drain Replacement

Five (5) copies of Sealed Bids, in response to Request for Bids for Route 5 Transfer Station Tipping Floor Trench Drain Replacement located at 29997 John P. Healy Drive, Harbeson, DE 19951, will be received by the Delaware Solid Waste Authority (DSWA) at the DSWA’S Dover office, 601 Energy Lane, Dover, Delaware 19901, until 2:00 p.m., on Tuesday, July 23, 2024, at which time all Bids will be opened and read aloud.  DSWA may extend the time and place for the opening for Bids by providing at least two (2) calendar days notice by certified mail, fax, or email to any Bidders who DSWA has recorded as having received a copy of the RFB.  If the Bid is submitted by mail or other delivery system, the sealed envelope containing the Bid shall be enclosed in a separate envelope plainly marked on the outside with the notation “Bid Enclosed.”  Bids delivered by any means other than by mail or personal delivery shall be rejected.

 

The project includes the replacement of the tipping floor trench drain at the Route 5 Transfer Station.  The work includes, but is not limited to, the demolition, removal, and replacement of the existing tipping floor trench drain. Additional information and details regarding the scope of work are included in the Project Manual.

 

A copy of the RFB for Contract C-23-881-SR may be obtained by emailing smg@dswa.com or submitting a request at https://dswa.com/resources/rfpbids/request-for-bidsproposals/ on or after Tuesday, June 18, 2024. DSWA will not be responsible for full or partial sets of the Project Manual obtained from any sources other than stated above or in the project manual, nor shall BIDDER rely upon such other sources or information.

 

A non-mandatory Pre-Bid Meeting has been scheduled for Tuesday, July 2, 2024 at 10:00 a.m. The location of the Pre-Bid Meeting is at the Route 5 Transfer Station located at 29997 John P. Healy Drive, Harbeson, DE 19951. It is the responsibility of the BIDDER to obtain an understanding of site conditions before preparing a bid.  Accordingly, BIDDERS are encouraged to attend the pre-bid meeting and/or schedule a site visit.

 

Each Bid, in excess of $200,000, shall be accompanied by a certified check or surety company bid bond, drawn to the order of the Delaware Solid Waste Authority on the form provided in the Project Manual and in an amount not less than ten percent (10%) of the “total bid price” as a guarantee that if the Bid is accepted, a contract will be entered into and the performance thereby properly secured.  Additional information regarding bid security appears in the Project Manual.

 

The BIDDER must submit, with its BID, documentation indicating it is licensed to conduct business in the State of Delaware and BIDDER must meet and comply with all state, local, and federal laws, regulations, ordinances, and requirements in the scope of their Work and comply with any and all licensing and permitting requirements.  All subcontractors used by the BIDDER must be licensed to conduct business in the State of Delaware prior to conducting any work on-site.  A copy of the form of the Agreement is contained in the Project Manual and will be awarded to the lowest responsive and responsible BIDDER who has neither been disqualified nor rejected pursuant to the terms of the Project Manual, and, which in DSWA’s judgement best serves its purposes.

 

The successful Bidder will be required to execute the Agreement, to furnish a performance bond and payment bond for the work each in the amount of one hundred percent (100%) of the “Total Bid Price” if the bid amount is more than $200,000, and to execute a Hold Harmless Agreement on forms provided in the Project Manual.  The successful bidder will also be required to furnish evidence of insurance coverage as required by the Project Manual and otherwise comply with terms and requirements of the Project Manual.

 

DSWA reserves the right to accept or reject any or all Bids which in its judgment is in the best interest of DSWA, and to waive any irregularities or informalities in the Bid or Bid process, and all BIDDERS are notified that such acceptance or rejection or waiver shall be without liability on the part of DSWA for any action brought against DSWA, any or all of its directors, or any DSWA agent, officer or employee, brought by any BIDDER because of such acceptance or rejection or waiver, nor shall any Bidder seek any recourse of any kind against such entity or individuals because of such acceptance or rejection or waiver.  Every BID prepared in response to this notice shall be prepared at the sole cost and expense of the BIDDER and shall be prepared by the BIDDER with the express understanding that any and all claims to reimbursement for the cost and expense of its preparation are waived.  The submittal of a bid in response to this notice shall constitute an agreement of the Bidder to all the provisions set forth in this notice and the Project Manual.

 

Five (5) copies of Bid shall be submitted to DSWA.  The Bids shall be, sealed, marked, and addressed as follows:

Delaware Solid Waste Authority

601 Energy Lane

Dover, Delaware 19901

Attention: Mike Lenkiewicz

Bid For: Route 5 Transfer Station Tipping Floor Trench Drain Replacement

Contract: C-23-881-SR

 

No BIDDER may withdraw their Bid within ninety (90) days after the actual date of opening thereof, except as may be authorized by the Project Manual.

 

The Project Manual explains the process by which prospective Bidders may submit questions about the meaning or intent of the Project Manual.  Please contact DSWA prior to the bid opening if you wish to schedule a site tour.

 

All other inquiries regarding this work shall be directed to:

Mike Lenkiewicz                                            and                              Simone George

Facility Manager/ Project Manager                                                 Administrative Assistant

Phone:  302-284-8851                                                                        Phone: 302-739-5361

Fax:     302-284-8136                                                                          Fax:  302-739-4287

Email:  mrl@dswa.com                                                                      Email:  smg@dswa.com

Cherry Island Landfill and Pigeon Point Landfill Manhole Rehabilitation- Phase 1

Join Zoom Meeting

https://us02web.zoom.us/j/83000391352?pwd=ldTeE8Vw4q3P8JgQjjcKLK6nBjaqa1.1

Meeting ID: 830 0039 1352

Passcode: 456630

Five (5) copies of Sealed Bids, in response to Request for Bids for Cherry Island Landfill and Pigeon Point Landfill Manhole Rehabilitation – Phase 1, in which Cherry Island Landfill (CIL) is located at 1706 E 12th Street, Wilmington, Delaware 19809, and Pigeon Point Landfill (PPLF) is located at 1101 Lambson Lane, New Castle, Delaware 19720, will be received by the Delaware Solid Waste Authority (DSWA) at the DSWA’S Dover office, 601 Energy Lane, Dover, Delaware 19901, until 2:00 p.m., on Tuesday, July 16, 2024, at which time all Bids will be opened and read aloud.  DSWA may extend the time and place of the opening for Bids by providing at least two (2) calendar days notice by certified mail, fax, or email to any Bidders who DSWA has recorded as having received an RFB.  If the Bid is submitted by mail or other delivery system, the sealed envelope containing the Bid shall be enclosed in a separate envelope plainly marked on the outside with the notation “Bid Enclosed.”  Bids delivered by any means other than by mail or personal delivery shall be rejected.

 

The project includes the rehabilitation of eighteen (18) manholes and two (2) pump stations at DSWA’s Cherry Island Landfill and Pigeon Point Landfill.  Manholes and pump stations vary in depth and condition and are part of the leachate collection system.  The positions of the manholes and pump stations can be seen in the Contract Drawings, in Appendix A.  The work includes, but is not limited to, mobilization and demobilization, surface preparations of each manhole for lining, which include but is not limited to, surface cleaning, removal of large debris, removal of existing liner, infiltration inspection, grouting, and rinsing; bypass pumping, replacement of a manhole cone, odor control, and lining of each manhole and pump station using 301-14 Warren Environmental Epoxy and testing.  Additional information and details regarding the scope of work are included in the Project Manual.

 

A copy of the RFB for Contract C-24-901-NCNP may be obtained by emailing smg@dswa.com or submitting a request at https://dswa.com/resources/rfpbids/request-for-bidsproposals/ on or after May 28, 2024.  DSWA will not be responsible for full or partial sets of the Project Manual obtained from any sources other than stated above or in the project manual, nor shall BIDDER rely upon such other sources or information.

 

A non-mandatory Pre-Bid Meeting has been scheduled for Thursday, June 6, 2024, at 10:00 a.m.  The location of the Pre-Bid Meeting is at the Cherry Island administration building located at 1706 E 12th Street, Wilmington, Delaware 19809. There will also be a Zoom meeting link that will be emailed to prospective BIDDERS who are recorded by DSWA as having received a copy of the Project Manual. The Zoom link will also be posted to DSWA’S website, https://dswa.com/resources/rfpbids/request-for-bidsproposals/ selecting the contract and clicking on the Contract number.  It is the responsibility of the BIDDER to obtain an understanding of site conditions before preparing a bid.  Accordingly, BIDDERS are encouraged to attend the pre-bid meeting and/or schedule a site visit.  A site visit will also be conducted after the Pre-Bid Meeting.

Each Bid, in excess of $200,000, shall be accompanied by a certified check or surety company bid bond, drawn to the order of the Delaware Solid Waste Authority on the form provided in the Project Manual and in an amount not less than ten percent (10%) of the “total bid price” as a guarantee that if the Bid is accepted, a contract will be entered into and the performance thereby properly secured.  Additional information regarding bid security appears in the Project Manual.

 

The BIDDER must submit, with its BID, documentation indicating it is licensed to conduct business in the State of Delaware and BIDDER must meet and comply with all state, local, and federal laws, regulations, ordinances, and requirements in the scope of their Work and comply with any and all licensing and permitting requirements.  All subcontractors used by the BIDDER must be licensed to conduct business in the State of Delaware prior to conducting any work on-site.  A copy of the bid form for this Request for Bids is contained in Section 00410 of the Project Manual and the form of Agreement is contained in Section 500 of the Project Manual. The BID will be awarded to the lowest responsive and responsible BIDDER who has neither been disqualified nor rejected pursuant to the terms of the Project Manual, and, which in DSWA’s judgement best serves its purposes.

 

The successful Bidder will be required to execute the Agreement, to furnish a performance bond and payment bond for the work each in the amount of one hundred percent (100%) of the “Total Bid Price” if the bid amount is more than $200,000, and to execute a Hold Harmless Agreement on forms provided in Section 00622 of the Project Manual.  The successful bidder will also be required to furnish evidence of insurance coverage as required by the Project Manual and otherwise comply with the terms and requirements of the Project Manual. BIDDER shall not alter or modify any of the forms contained in the Project Manual.

 

DSWA reserves the right to accept or reject any or all Bids which in its judgment is in the best interest of DSWA, and to waive any irregularities or informalities in the Bid or Bid process, and all BIDDERS are notified that such acceptance or rejection or waiver shall be without liability on the part of DSWA for any action brought against DSWA, any or all of its directors, or any DSWA agent, officer or employee, brought by any BIDDER because of such acceptance or rejection or waiver, nor shall any Bidder seek any recourse of any kind against such entity or individuals because of such acceptance or rejection or waiver.  Every BID prepared in response to this notice shall be prepared at the sole cost and expense of the BIDDER and shall be prepared by the BIDDER with the express understanding that any and all claims to reimbursement for the cost and expense of its preparation are waived.  The submittal of a bid in response to this notice shall constitute an agreement of the Bidder to all the provisions set forth in this notice and the Project Manual.

 

Five (5) copies of the BID shall be submitted to DSWA.  The BIDS shall be, sealed, marked, and addressed as follows:

Delaware Solid Waste Authority

601 Energy Lane

Dover, Delaware 19901

Attention: Renee Hetrick

Bid for: CIL and PPLF Manhole Rehabilitation – Phase 1

Contract C-24-901-NCNP

 

No BIDDER may withdraw their Bid within one hundred-twenty (120) days after the actual date of opening thereof, except as may be authorized by the Project Manual.

 

The Project Manual explains the process by which prospective Bidders may submit questions about the

meaning or intent of the Project Manual.

 

All other inquiries regarding this work shall be directed to:

 

Renee Hetrick                                     and                              Simone George

Project Manager                                                                      Administrative Assistant

Phone:  302-739-5361                                                            Phone:  302-739-5361

Email:  reh@dswa.com                                                           Email:  smg@dswa.com

Fax:  302-739-4287                                                                Fax:  302-739-4287

Capping of Area A/B at the Central Solid Waste Management Center

Five (5) copies of Sealed Bids, in response to Request for Bids for Capping of Area A/B at the Central
Solid Waste Management Center, located at 1107 Willow Grove Road, Felton, DE 19943, will be
received by the Delaware Solid Waste Authority (DSWA) at the DSWA’S Dover office, 601 Energy
Lane, Dover, Delaware, until 2:00 p.m., on Tuesday, June 25, 2024,  at which time all Bids will be
opened and read aloud. DSWA may extend the time and place for the opening for Bids by providing at
least two (2) calendar days notice by certified mail, fax, or email to any Bidders who DSWA has
recorded as having received an RFB. If the Bid is submitted by mail or other delivery system, the
sealed envelope containing the Bid shall be enclosed in a separate envelope plainly marked on the
outside with the notation “Bid Enclosed.” Bids delivered by any means other than by mail or personal
delivery shall be rejected.

The project includes removal of the existing phytocap and other existing infrastructure, such as the
wetland treatment system; spray irrigation system, relocation of solar array, installation of Subtitle D
Landfill Cap, construction of a new sediment pond, conversion of existing treated effluent storage
pond to a sediment pond, modifications to the landfill gas system and replacement of landfill gas
header at Area A/B. The work includes, but is not limited to, surveying before, during and after
construction; stripping of vegetative layer, clearing and grading; installation of the capping system and
connecting to cleanouts and pump stations; constructing diversion berms; and appurtenant items as
described in the project manual. Additional information and details regarding the scope of work are
included in the Project Manual. The bid forms shall not be modified or altered by BIDDER.

The Project Manual shall be available Wednesday, May 15, 2024 at DSWA’s Administrative Office
located at 601 Energy Lane, Dover, DE 19901. The Project Manual may be examined by appointment
or obtained without cost at DSWA’s Dover Administration Office at the above address, Monday
through Friday, during regular working hours, 8:00 a.m. to 4:30 p.m. A copy of the RFB for Contract
C-24-900-CS may also be obtained by emailing smg@dswa.com or submitting a request at
https://dswa.com/resources/rfpbids/request-for-bidsproposals/ on or after May 15, 2024. DSWA will
not be responsible for full or partial sets of the Project Manual obtained from any sources other than
stated above, or in the project manual, nor shall BIDDER rely upon such other sources or information.

A non-mandatory Pre-Bid Meeting has been scheduled for Tuesday, June 4, 2024 at 10:00 a.m.
The location of the Pre-Bid Meeting is at the Central Solid Waste Management Center (CSWMC)
located at 1107 Willow Grove Road, Felton, DE 19943. It is the responsibility of the BIDDER to
obtain an understanding of site conditions before preparing a bid. Accordingly, BIDDERS are
encouraged to attend the pre-bid meeting and/or schedule a site visit.

Each Bid, in excess of $200,000, shall be accompanied by a certified check or surety company bid
bond, drawn to the order of the Delaware Solid Waste Authority on the form provided in the Project
Manual and in an amount not less than ten percent of the “total bid price” as a guarantee that if the Bid
is accepted, a contract will be entered into and the performance thereby properly secured. Additional
information regarding bid security appears in the Project Manual.

The BIDDER must submit, with its BID, documentation indicating it is licensed to conduct business in
the State of Delaware and BIDDER must meet and comply with all state, local, and federal laws,
regulations, ordinances, and requirements in the scope of their Work and comply with any and all
licensing and permitting requirements. All subcontractors used by the BIDDER must be licensed to
conduct business in the State of Delaware prior to conducting any work on-site. A copy of the form of
the Agreement is contained in the Project Manual and will be awarded to the lowest responsive and
responsible BIDDER who has neither been disqualified nor rejected pursuant to the terms of the
Project Manual, and, which in DSWA’s judgement best serves its purposes.

The successful Bidder will be required to execute the Agreement, to furnish a performance bond and
payment bond for the work each in the amount of one hundred percent (100%) of the “Total Bid Price”
if the bid amount is more than $200,000, and to execute a Hold Harmless Agreement on forms
provided in the Project Manual. The successful bidder will also be required to furnish evidence of
insurance coverage as required by the Project Manual and otherwise comply with terms and
requirements of the Project Manual.

DSWA reserves the right to accept or reject any or all Bids which in its judgment is in the best interest
of DSWA, and to waive any irregularities or informalities in the Bid or Bid process, and all BIDDERS
are notified that such acceptance or rejection or waiver shall be without liability on the part of DSWA
for any action brought against DSWA, any or all of its directors, or any DSWA agent, officer or
employee, brought by any BIDDER because of such acceptance or rejection or waiver, nor shall any
Bidder seek any recourse of any kind against such entity or individuals because of such acceptance or
rejection or waiver. Every BID prepared in response to this notice shall be prepared at the sole cost
and expense of the BIDDER and shall be prepared by the BIDDER with the express understanding that
any and all claims to reimbursement for the cost and expense of its preparation are waived. The
submittal of a bid in response to this notice shall constitute an agreement of the Bidder to all the
provisions set forth in this notice and the Project Manual.

Five (5) copies of Bid shall be submitted to DSWA. The Bids shall be, sealed, marked, and addressed
as follows:

Delaware Solid Waste Authority
601 Energy Lane
Dover, Delaware 19901
Attention: Robert Roth
Bid For: Capping of Area A/B at the Central Solids Waste Management Center
Contract C-24-900-CS

 

No BIDDER may withdraw their Bid within one hundred twenty (120) days after the actual date of
opening thereof, except as may be authorized by the Project Manual.

The Project Manual explains the process by which prospective Bidders may submit questions about the
meaning or intent of the Project Manual. Please contact DSWA prior to the bid opening if you wish to
schedule a site tour.

All other inquiries regarding this work shall be directed to:

Robert Roth                        and                  Simone George
Project Manager                                         Administrative Assistant
Phone: 302-739-5361                                Phone: 302-739-5361
Fax: 302-739-4287                                    Fax: 302-739-4287
Email: rr@dswa.com                                Email: smg@dswa.com

Demolition of Digesters at the DRC

Five (5) copies of Sealed Bids, in response to Request for Bids for Demolition of Digesters at the Delaware Recycling Center (DRC), located at 1101 Lambson Lane New Castle, DE 19720, will be received by the Delaware Solid Waste Authority (DSWA) at the DSWA’S Dover office, 601 Energy Lane, Dover, Delaware, until 2:00 p.m., on Tuesday, March 19, 2024, at which time all Bids will be opened and read aloud.  DSWA may extend the time and place for the opening for Bids by providing at least two (2) calendar days’ notice by certified mail, fax, or email to any Bidders who DSWA has recorded as having received an RFB.  If the Bid is submitted by mail or other delivery system, the sealed envelope containing the Bid shall be enclosed in a separate envelope plainly marked on the outside with the notation “Bid Enclosed.”  Bids delivered by any means other than by mail or personal delivery shall be rejected.

 

This project includes the demolition and removal of the Digester buildings and Concrete Pads located at the DRC. The work includes, but is not limited to, existing site evaluation, including all equipment, utilities and features inside of the demolition area; preparation of site to remove any standing water or other issues that might have arisen due to the building having been abandoned since 1991; preparation and furnishment of all required equipment, labor, materials, permits, and incidentals necessary to demolish all requested features; removal and transport of all debris to the appropriate locations; and backfilling of demolished areas as requested by DSWA. Additional information and details regarding the scope of work are included in the Project Manual.

 

A copy of the RFB for Contract C-23-892-ND may be obtained by emailing smg@dswa.com or submitting a request at https://dswa.com/resources/rfpbids/request-for-bidsproposals/ on or after Tuesday, February 6, 2024.  DSWA will not be responsible for full or partial sets of the Project Manual obtained from any sources other than stated above, or in the project manual, nor shall BIDDER rely upon such other sources or information.

 

A non-mandatory Pre-Bid Meeting has been scheduled for Wednesday, February 14, 2024, at 10:00 a.m.  The location of the Pre-Bid Meeting is at the Delaware Recycling Center (DRC) located at 1101 Lambson Lane New Castle, DE 19720. It is the responsibility of the BIDDER to obtain an understanding of site conditions before preparing a bid.  Accordingly, BIDDERS are encouraged to attend the pre-bid meeting and/or schedule a site visit.

 

Each Bid, in excess of $200,000, shall be accompanied by a certified check or surety company bid bond, drawn to the order of the Delaware Solid Waste Authority on the form provided in the Project Manual and in an amount not less than ten percent of the “total bid price” as a guarantee that if the Bid is accepted, a contract will be entered into and the performance thereby properly secured.  Additional information regarding bid security appears in the Project Manual.

 

The BIDDER must submit, with its BID, documentation indicating it is licensed to conduct business in the State of Delaware and BIDDER must meet and comply with all state, local, and federal laws, regulations, ordinances, and requirements in the scope of their Work and comply with any and all licensing and permitting requirements.  All subcontractors used by the BIDDER must be licensed to conduct business in the State of Delaware prior to conducting any work on-site.  A copy of the form of the Agreement is contained in the Project Manual and will be awarded to the lowest responsive and responsible BIDDER who has neither been disqualified nor rejected pursuant to the terms of the Project Manual, and, which in DSWA’s judgement best serves its purposes.

 

The successful Bidder will be required to execute the Agreement, to furnish a performance bond and payment bond for the work each in the amount of one hundred percent (100%) of the “Total Bid Price” if the bid amount is more than $200,000, and to execute a Hold Harmless Agreement on forms provided in the Project Manual.  The successful bidder will also be required to furnish evidence of insurance coverage as required by the Project Manual and otherwise comply with terms and requirements of the Project Manual. Bidders shall not alter the project manual or forms or any documents contained therein.

 

DSWA reserves the right to accept or reject any or all Bids which in its judgment is in the best interest of DSWA, and to waive any irregularities or informalities in the Bid or Bid process, and all BIDDERS are notified that such acceptance or rejection or waiver shall be without liability on the part of DSWA for any action brought against DSWA, any or all of its directors, or any DSWA agent, officer or employee, brought by any BIDDER because of such acceptance or rejection or waiver, nor shall any Bidder seek any recourse of any kind against such entity or individuals because of such acceptance or rejection or waiver.  Every BID prepared in response to this notice shall be prepared at the sole cost and expense of the BIDDER and shall be prepared by the BIDDER with the express understanding that any and all claims to reimbursement for the cost and expense of its preparation are waived.  The submittal of a bid in response to this notice shall constitute an agreement of the Bidder to all the provisions set forth in this notice and the Project Manual.

 

Five (5) copies of Bid shall be submitted to DSWA.  The Bids shall be, sealed, marked, and addressed as follows:

Delaware Solid Waste Authority

601 Energy Lane

Dover, Delaware 19901

Attention: Christopher Velazquez

Bid For: Demolition of Digesters at the DRC

Contract C-23-892-ND

 

No BIDDER may withdraw their Bid within ninety (90) days after the actual date of opening thereof, except as may be authorized by the Project Manual.

 

The Project Manual explains the process by which prospective Bidders may submit questions about the meaning or intent of the Project Manual.  Please contact DSWA prior to the bid opening if you wish to schedule a site tour.

 

All other inquiries regarding this work shall be directed to:

Christopher Velazquez                       and                              Simone George

Project Engineer                                                                     Administrative Assistant

Phone:  302-739-5361                                                            Phone:  302-739-5361

Fax:  302-739-4287                                                                Fax:  302-739-4287

Email:  cav@dswa.com                                                          Email:  smg@dswa.com